When this client came to us requesting supply and installation of a temporary portable bridge over an existing 9m clear span pool to enable construction equipment including forklifts and mini excavators to access the other side of the pool….as usual we said no problems.
I must say though this installation was somewhat a little more unusual than others. As you can see from the photo below it took a bit of thought and effort just to get it into the building.

Unfortunately, we couldn’t just simply crane the temporary bridge into position as we usually would. To complicate the matter even further we only had a narrow opening of 2.4m wide to get the bridge into the swimming pool complex.That really made it challenging…
And we are always up for a challenge !
But the complications did not stop there… We also only had one edge of the pool on which to support the bridge as it was being manoeuvred into position. Now we really needed to be creative
…

Now I don’t want to give too much away here,
Yes it was complicated,
But if you want to find out how we did it,
I suggest that you give Preston Hire a call on 03 9399 1890
Oh and by the way, thanks to a skillful crane operator and a few other tricks this temporary bridge was installed in less than 2 hrs.
Do you have a special requirement for a temporary portable bridge on your next project?
At Preston, we have a wide range of solutions to suit your needs. So if you need a temporary bridge that is also a portable bridge, Call 03 9399 1890 NOW!
“Preston Hire equipment works, it’s safe and...
“Safety is No. 1 for us and we know it is for Preston...
“Preston Hire offer good products and their organisation...
“Preston Hire truly are leaders in their field....